North American LNG Import Terminals
As of December 2004, there were four operating liquefied natural gas (LNG)
import terminals in North America with a combined peak sendout capacity of
3.715 Bcf/d and expansion plans for another 2.44 Bcf/d of sendout capacity. In
addition, there were plans for another 49 LNG import terminals with an expected
total combined peak sendout capacity of more than 49 Bcf/d. Of those 49
terminals, nine, with a total peak sendout of 10.9 Bcf/d, had received final
regulatory approvals. Another 22 projects are already in various stages of the
regulatory approval process, and 18 additional LNG projects remain in the
planning stages.
Operating Terminals:
- Cove Point LNG (Planned Expansion) -- Lusby, Maryland;
Dominion; Sendout 1 Bcf/d; Planned expansion would add 0.8 Bcf/d of sendout
capacity in 2008; Storage capacity rose from 5 Bcf to 7.8 Bcf in December 2004
through the addition of a new 2.8 Bcf LNG storage tank. Storage is expected to
increase to 14.6 Bcf in 2008. The 2008 expansion project also would include 47
miles of looping along the Cove Point Pipeline in Maryland, a new 81-mile
pipeline in Pennsylvania between Perulack, PA, and Leidy, PA, and various
smaller new pipelines and looping projects in Pennsylvania designed to increase
transportation of gas between the import terminal and Dominion's many gas
storage fields that serve the Northeast and Mid Atlantic regions. Dominion
received FERC authorization Aug. 17, 2004 to begin the NEPA prefiling process
on the 2008 project. The company held an open season in fall 2004 and said the
project was fully subscribed. Statoil has signed a contract for 1.05 Bcf/d of
the total 1.8 Bcf/d of planned send-out capacity in the 2008 expansion project.
The remaining 750 MMcf/d of capacity will be owned by Shell, BP and peaking
customers. In 2003, the company completed its Cove Point East pipeline
expansion, which included two new compressor stations with 19,340 of horsepower
in Loudoun and Fairfax counties, VA. The $43.5 million project added 445,000
Dth/d in additional firm transportation capacity for Washington Gas Light and
Virginia Power Service Energy Corp. FERC approved the resumption of LNG imports
at Cove Point in October 2001. The terminal received its first commercial
delivery in 23 years in August 2003 from Trinidad and Tobago. Cove Point was
originally constructed in the mid 1970s at a cost of $400 million.
- Elba Island (Expanding) -- Elba Island, Georgia; El Paso;
Average sendout 0.44 Bcf/d; Peak sendout 0.68 Bcf/d; Expansion approved by FERC
in April 2003 allows the company to add 3.3 Bcf of storage capacity and boost
the average sendout rate of the terminal by 0.36 Bcf/d (peak sendout by 0.54
Bcf/d), bringing total storage capacity to 7.3 Bcf and the average sendout rate
to about 0.8 Bcf/d. The $148 million project has a targeted completion in the
first quarter of 2006. Shell Gas & Power has entered into a binding
precedent agreement with Southern LNG to acquire all of the expansion capacity
for a 30-year term. Marathon signed contract in 2002 to deliver 58 Bcf/year of
LNG to Elba Island for 17 years; BG Group holds rights through December 2023 to
market 446 MMcf/d of sendout capacity, including 159 MMcf/d from LNG delivered
by Marathon and LNG delivered by BG from Atlantic LNG trains 2 and 3 in
Trinidad. Terminal was given authorization by FERC in December 1999 to resume
import operations after being idled for 20 years and received its first new
shipment on Oct. 2, 2003 from a tanker that was barred from entering the
Distrigas terminal in Boston Harbor because of security and safety
concerns.
- Everett LNG -- Everett, Massachusetts; Distrigas of
Massachusetts Corp. (Tractebel LNG/Suez); Peak sendout capacity 1.035 Bcf/d;
Storage capacity 3.4 Bcf (42 million gallons) in two storage tanks. Distrigas
expanded its baseload sendout capacity by 300 MMcf/d to 725 MMcf/d in 2003.
Distrigas serves about 20% of New England's annual gas demand. The Distrigas
terminal is connected to Algonquin Gas Transmission, Tennessee Gas Pipeline and
KeySpan's gas distribution system. Distrigas also provides LNG to customers
that have LNG storage tanks through four truck loading bays with a maximum
liquid sendout of more than 100 MMcf/d or 1.2 million gallons/day. The terminal
received its first shipment of LNG in November 1971.
- Trunkline LNG (Phase I Expansion Approved; Phase II Pending at
FERC) --> Lake Charles, Louisiana; Panhandle Energy (Southern Union);
Average sendout capacity 0.63 Bcf/d; Peak sendout capacity 1 Bcf/d; Storage
capacity 6.3 Bcf. In December 2002, FERC approved Trunkline LNG's plans to
expand the facility to 1.2 Bcf/d of average sendout capacity (1.3 Bcf/d of peak
sendout) and 9 Bcf of storage capacity. Plans call for construction of a fourth
storage tank and a second unloading dock, giving it the ability to unload two
ships simultaneously. The cost of the expansion is $177.2 million, and it has a
targeted in-service date of December 2005. A second proposed expansion was
filed with FERC in January 2004 and approved in September. It would bring
average sendout capacity to 1.8 Bcf/d with peak sendout of 2.1 Bcf/d by mid
2006. The project also calls for the construction of a 23-mile, 36-inch
diameter pipeline from the LNG terminal to the mainline of Trunkline Gas, and
for construction of additional pumps and vaporizers along with unloading
facilities added to a second dock. The new pipeline would parallel an existing
pipeline, increasing pipeline capacity from the terminal to 2.1 Bcf/d from 1.3
Bcf/d. BG Group has rights to entire sendout capacity.
Planned and Proposed Terminals
Atlantic Coast
- Bear Head (Granted Environmental Approval by Canadian and
Provincial Governments) -- Point Tupper, Nova Scotia; Access Northeast
Energy (purchased by Anadarko); Sendout 1 Bcf/d after Phase I; Service November
2007. The two-phase project involves construction and operation of a 7.5
million ton/year capacity marine LNG terminal, land-based storage tanks and a
land-based regasification area with a gas sendout capacity of 1 Bcf/d in Phase
I and future expansion of sendout capacity to 1.5 Bcf/d in Phase II. The
facilities would deliver gas into the Maritimes and Northeast Pipeline, which
serves eastern Canada and Northeast U.S. markets. Nova Scotia Department of
Environment and Labour and Canadian Environmental Assessment Agency concluded
in August 2004 that the terminal, proposed for construction at the Point
Tupper/Bear Head Industrial Park on the Strait of Canso, is not likely to cause
significant adverse effects on the environment. It is the first of several
approvals required before the company can begin construction.
- Brayton Point LNG (Planned) -- Somerset, Massachusetts, near
Brayton Point Station; Somerset LNG; Peak sendout 0.65 Bcf/d.
- Broadwater Energy (Planned) -- 11 miles offshore Connecticut
in Long Island Sound; TransCanada Corp. and Shell US Gas & Power LLC;
Average sendout 1 Bcf/d; Cost $700 million; Service in late 2010. The floating
port facility will use a closed system for vaporizers that will not include the
use of seawater from the Sound. It will include a 25-mile subsea pipeline to
the Iroquois Gas Transmission system. Website: http://www.broadwaterenergy.com/.
- Cacouna Energy (Planned) -- Gros Cacouna, Quebec, about nine
miles northeast of Riviere-du-Loup; TransCanada/Petro-Canada; Cost C$660
million; Sendout 0.5 Bcf/d. Project was announced in late August 2004.
Petro-Canada has signed a memorandum of understanding with Russia's Gazprom
that could involve operations in all areas of the LNG value chain, from
exploration, production and liquefaction, to shipping, regasification and
marketing in North America. The agreement covers options for joint development
of a US$1.2-1.5 billion liquefaction plant near St. Petersburg, Russia in the
Baltic port of Ust Luga, and to investigate options for gas supplies to that
LNG plant and then to regasification terminals in North America by 2009.
- Calypso (FERC Approved Pipeline; Bahamas Granted Preliminary
Approval) -- Freeport Grand Bahama Island, Bahamas; Tractebel LNG; Sendout
0.83 Bcf/d; Service expected in 2007. The $132 million 54-mile U.S. portion of
the pipeline system between the offshore international boundary and Port
Everglades, FL, in Broward County was approved by FERC in March 2004. The U.S.
segment of the pipeline, which will have a capacity to deliver 832,000 Dth/d of
gas, would travel onshore to a proposed interconnection with Florida Gas
Transmission adjacent to Florida Power & Light's (FPL) Ft. Lauderdale power
plant. The terminal application is pending in Bahamas. The Bahamian
environmental commission is expected to rule soon on the project, which already
has preliminary commercial approval from the Ministry of Trade and Industry.
Tractebel announced an agreement in December 2004 to combine its Calypso
project with El Paso's Seafarer/High Rock LNG project. The companies plan to
pursue full regulatory approval of both projects but will move forward with
only one, or a combination, of them. FPL Group Resources has an option to buy
the Seafarer/High Rock LNG project from El Paso.
- Canaport (Approved by Canadian and Provincial Governments) --
St John, New Brunswick; Irving Oil; C$500 million; Sendout 1 Bcf/d; Storage
capacity 480,000 cubic meters in three 160,000 cubic meter tanks. Canaport
received final approval from Canadian agencies in August 2004. Approvals were
issued by the New Brunswick Department of Environment and Local Government,
Environment Canada, and Fisheries and Oceans Canada, in accordance with the
provincial Environmental Assessment Regulations and the federal Canadian
Environmental Assessment Act. The facility will be located 65 miles from the
U.S. border and will be connected via pipeline to the 250,000 bbl/d Irving Oil
refinery, which is five miles away.
- Crown Landing (Pending at FERC) -- Logan Township, New Jersey,
adjacent to Delaware River; BP; Sendout 1.2 Bcf/d; Service 2009; Connections
planned to three major Northeast interstate pipelines.
- Freedom Energy Center (Planned) -- Philadelphia, PA,
along the Delaware River; Philadelphia Gas Works; Sendout 0.6 Bcf/d; Project
would involve conversion of PGW's existing Port Richmond LNG plant into an
import terminal near the Tioga Marine Terminal on the North Delaware
Riverfront. The existing plant, which was built in the early 1970s as a means
of ensuring a reliable supply of natural gas for Philadelphia, currently has
about 23.5 MMcf/d of natural gas liquefaction capacity, two storage tanks
capable of holding a total of about 4.1 Bcf of gas and vaporization capacity
totaling about 450 MMcf/d. It is the largest peak shaving LNG plant in North
America.
- High Rock LNG (Pipeline Pending at FERC; Terminal Pending in
Bahamas) -- Grand Bahama Island, Bahamas; El Paso (FPL Group has option to
buy 100% of the project); Sendout 1 Bcf/d. The U.S. portion of the $226
million, 163-mile Seafarer Pipeline is pending at FERC. The High Rock LNG
terminal on Grand Bahama Island is pending in Bahamas. Tractebel announced an
agreement in December 2004 to combine its Calypso project with El Paso's
Seafarer/High Rock LNG project. The companies plan to pursue full regulatory
approval of both projects but will move forward with only one, or a
combination, of them.
- Keltic LNG (Planned) -- Goldboro, Nova Scotia; Keltic
Petrochemicals; Sendout 0.5 Bcf/d in 2007, 1.9 Bcf/d in 2009; Terminal to be
located at the beginning of the Maritimes and Northeast Pipeline system.
- Northeast Gateway (Planned) -- offshore Gloucester,
Massachusetts; Excelerate Energy LLC; Sendout 0.8 Bcf/d; Cost $200 million;
Service 2007; Expected to be connected to Duke Energy's HubLine pipeline system
in Massachusetts Bay through 12 miles of 24-inch diameter pipeline.
- Ocean Express (FERC Approved Pipeline; Terminal Pending in
Bahamas) -- Ocean Cay, Bahamas; AES Corp.; Sendout 0.84 Bcf/d; Service in
mid 2006. The 54-mile U.S. pipeline portion of the $440 million project has
been approved by FERC. The LNG terminal is pending in Bahamas. AES is dredging
sand and soil to create its own 90-acre industrial island, called Ocean Cay,
for its LNG terminal.
- Point Tupper (Planned) -- Statia Terminals Canada; Sendout
0.5 Bcf/d. Statia Terminals operates the Point Tupper terminal in the Strait of
Canso in Nova Scotia. Its primary function is transshipment of crude oil and
refined petroleum products. It has 1.2 million cubic meters of capacity.
- Providence LNG (Pending at FERC; Received DEIS) -- Fields
Point, Rhode Island; KeySpan/BG Group; Sendout 0.525 Bcf/d; Cost $50 million;
Service in November 2005. KeySpan filed a plan with FERC in April 2004 to
convert the existing 600,000 bbl LNG storage terminal in Providence, RI, to an
import terminal. KeySpan signed an agreement in October 2003 with BG Group to
undertake the conversion project. Algonquin Gas Transmission plans to build
1.44 miles of 24-inch pipe with 500 MMcf/d of transportation capacity to
connect to the KeySpan facility with service in November 2005; LNG terminal
project has encountered opposition from Rhode Island Attorney General Patrick
C. Lynch and Rhode Island Gov. Donald L. Carcieri because of safety and
security concerns. FERC granted the terminal a favorable draft environmental
impact statement in December 2004.
- Rabaska (Pending at Canadian and Provincial Agencies) --
Ville Guay, Quebec; Gaz Metro, Enbridge, Gaz de France; Cost C$700 million; 0.5
Bcf/d; Storage 320,000 cubic meters in two tanks each with capacity of 160,000
cubic meters; Service in first quarter of 2009.
- Quoddy Bay (Planned) -- Pleasant Point, ME (near Perry,
Maine, in Washington County); Passamaquoddy/Sipayik Reservation; Sendout 0.5
Bcf/d, expandable to 1 Bcf/d; Cost $400 million. The terminal would be located
adjacent to the commercial shipping port at Eastport, ME, 40 miles east of the
Maritimes and Northeast Pipeline. Members of the Passamaquoddy Native American
tribe voted in August 2004 in favor of locating the import terminal on their
Sipayik Reservation on Passamaquoddy Bay on the northern Maine coast. Project
sponsors Quoddy Bay LLC plan to file FERC application in December 2004.
- Weaver's Cove (Pending at FERC; Received DEIS) -- Fall River,
MA; Poten & Partners/Amerada Hess; Sendout of 0.4 Bcf/d on average and 0.8
Bcf/d at peak; 0.1 Bcf/d deliverable by truck; Storage capacity for 4.4 Bcf;
Cost $250 million. The project would take up 68 acres of the 73-acre site on
the Taunton River feeding into Mount Hope Bay and Narragansett Bay, about 50
miles south of Boston. FERC issued a favorable draft environmental impact
statement on the project in August 2004, but noted there was local opposition
and the project would need Coastal Zone Consistency Reviews in Massachusetts
and Rhode Island.
Gulf Coast
- Altamira (Approved by State and Federal Mexican Agencies) --
Altamira, Tamaulipas, Mexico; Shell/Total; Sendout 0.5 Bcf/d, expandable to 1.3
Bcf/d; Two storage tanks, each with a capacity of 150,000 cubic meters; Project
cost $370 million; Construction has started.
- Calhoun LNG (Planned) -- Port Lavaca, TX; Gulf Coast LNG
Partners; Peak sendout 1 Bcf/d; Cost $400 million; Two 3.5 Bcf storage
tanks.
- Cameron LNG (Approved by FERC) -- Hackberry, Louisiana, 15
miles south of Lake Charles; Sempra Energy; Peak sendout 1.5 Bcf/d; Service
2007; Cost $700 million. Sempra expects to have supply agreements in place
before the end of the year but supply available to North America is expected to
be tight until 2008, according to CEO Stephen Baum.
- Compass Port (Pending at Coast Guard/Maritime
Administration) -- Gulf of Mexico offshore Alabama (11 miles south of
Dauphin Island); Compass Port LLC (ConocoPhillips); Sendout 1 Bcf/d; Storage
capacity 300,000 cubic meters in two storage tanks; Cost $500-800 million;
Awaiting Coast Guard approval. The Coast Guard held scoping meetings in April
regarding the proposed pipeline system and is expected to release a draft
environmental impact statement on the project in the next few months. Compass
Port would connect with Gulfstream Natural Gas System, Transcontinental Gas
Pipe Line and Gulf South Pipeline Co. LP. The proposed 31 mile takeaway
pipeline would have the capacity to transport 1 Bcf/d.
- Corpus Christi (Pending at FERC, Received DEIS) -- Corpus
Christi, Texas; Cheniere LNG; Sendout capacity 2.6 Bcf/d; Three 160,000 cubic
meter storage tanks; Service in late 2007. Cheniere received favorable a draft
environmental impact statement from FERC in November 2004.
- Creole Trail (Planned) -- mouth of the Calcasieu Channel in
Cameron Parish, LA; Cheniere LNG; Peak sendout 2.6 Bcf/d, two docks, three
160,000-cubic-meter storage tanks (10.1 Bcf of capacity).
- Freeport LNG (Approved by FERC) -- Freeport, TX, on Quintana
Island in Brazoria County; Cheniere/Contango/ConocoPhillips/Dow Chemical;
Project cost $500 million; Sendout 1.5 Bcf/d; Storage capacity 7 Bcf; 9.4 mile
pipeline to Stratton Ridge. Service in second half of 2007; On June, 18, 2004,
FERC awarded Freeport LNG Development LP authorization under Section 3 of the
Natural Gas Act to site, construct and operate the import terminal.
ConocoPhillips has signed an agreement to fund construction of the terminal in
exchange for 1 Bcf/d of the regasification capacity.
- Golden Pass (Pending at FERC) -- Sabine Pass, Texas, 10 miles
south of Port Arthur; ExxonMobil; 1 Bcf/d, expandable to 2 Bcf/d; Project cost
$600 million; Service in late 2008; Project could include two 36-inch diameter
pipelines, one 43 miles long and the other 77 miles long, to an intrastate
pipeline in Orange County, TX, and interstate lines in Calcasieu Parish, LA. In
addition, a two-mile 24-inch diameter line would carry gas to ExxonMobil's
Beaumont refinery. ExxonMobil and Qatar Petroleum have signed an agreement to
supply 15.6 million tons a year of LNG (2 Bcf/d) to the United States from
Qatar for 25 years. Filed with FERC in November 2003.
- Gulf Landing (Pending at Coast Guard/Maritime Administration)
-- West Cameron Block 213 about 38 miles offshore, Louisiana; Shell US Gas
& Power LLC (Royal Dutch/Shell); Service in 2008 or 2009; Sendout 1
Bcf/d.
- Gulf LNG Energy (Pending at FERC) -- Pascagoula, MS; Gulf LNG
Energy LLC; Average sendout 1 Bcf/d; Cost $450 million; Service expected in
2009; Gulf LNG Energy, which began the National Environmental Policy Act
pre-filing process at FERC in December, has executed an agreement with the Port
of Pascagoula for the right to build the LNG terminal on lands in Bayou Casotte
that are owned or controlled by the Jackson County Port Authority.
- HiLoad LNG (Planned) -- offshore Tamaulipas, Mexico; Peak
sendout 1.4 Bcf/d; San Antonio-based Tidelands Oil & Gas Corp. The project
would be capable of delivering 500 MMBtu/d to Mexico; 450 MMBtu/d to proposed
storage in Mexico's Burgos Basin and 500 MMBtu/d to U.S. markets. Tidelands has
signed an agreement with Remora Technology to use Remora's HiLoad LNG
Regasification Terminal design, which has been funded in part by
ConocoPhillips. The design is for a floating terminal that attaches to an LNG
tanker and directly vaporizes the LNG as it is offloaded, eliminating the need
for above ground storage tanks. The terminal will inject gas directly into
offshore pipelines at rates between 250 MMcf/d and 1.4 Bcf/d.
- Ingleside Energy Center (Pending at FERC) -- Ingleside,
Texas, near Corpus Christi; Occidental Petroleum; Cost $400 million; Sendout 1
Bcf/d; Service 2007; Started NEPA pre-filing process at FERC in April 2004 and
certificate application was filed in November; The terminal will have two LNG
storage tanks, each with a capacity of one million barrels. The terminal will
be capable of unloading 140 ships per year. Occidental said it plans to use
only about 10% of the proposed send-out capacity from the terminal for its own
operations, with the remainder of the LNG-sourced gas going directly into
intrastate and interstate pipelines serving the southern, midwestern and
eastern markets. Occidental affiliate San Patricio Pipeline LLC filed an
application to build a 26-mile, 1 Bcf/d pipeline that would extend from the
proposed terminal along the Texas coast to interconnections with nine existing
intrastate and interstate pipelines.
- Louisiana Energy Bridge (Approved by Coast Guard/Maritime
Administration) -- offshore Louisiana (40 miles offshore); El Paso
Corp./Excelerate Energy LLC; Sendout 0.5 Bcf/d; Cost $60 million; Service in
early 2005; Approved by the Coast Guard. A Korean company is building three
specialized 138,000 cubic meter LNG cargo ships for Excelerate. The ships are
being built with unique and untested onboard regasification systems that will
allow them to deliver regassified LNG into specialized buoys offshore that will
be connected to pipelines that will bring the gas to shore. The terminal is
expected to be operational in January 2005, but it probably will not receive
first spot cargo deliveries until mid 2005 or later because of constraints on
the supply side. Excelerate said there are 10 liquefaction projects under
construction, five of which are due online in 2005. Two liquefaction trains are
being built in Egypt, two in Nigeria and one in Trinidad. As of June 2004,
Excelerate had not lined up long-term supply or market agreements for its
Louisiana Energy Bridge. The company also is planning an Energy Bridge offshore
Gloucester, MA.
- Main Pass Energy Hub (Pipeline Pending at FERC; Terminal Pending
at Coast Guard/Maritime Administration) -- Main Pass Block 299 offshore,
Louisiana, 37 miles east of Venice, LA; Freeport-McMoRan; Service in late 2007;
Cost $440 million; Sendout 1 Bcf/d; Storage capacity of 250,000 cubic meters.
The project includes a proposed 28 Bcf salt dome natural gas storage facility
with peak deliverability (including terminal vaporization) of 2.5 Bcf/d. A
terminal application has been filed with the Coast Guard and a pipeline
application was filed with FERC in March 2004 (watch McMoRan's Main
Pass Energy Hub Video). Website: http://www.mpeh.com/.
- Pearl Crossing (Pending with Coast Guard/Maritime
Administration) -- Gulf of Mexico offshore Louisiana, 40 miles south of
Cameron Parish; ExxonMobil; Sendout 1 Bcf/d with expansion capability to 2
Bcf/d; Startup in 2008; Filed in May with Coast Guard. Two storage tanks with
125,000 cubic meters each. Two 42-inch diameter pipeline to Starks, LA.
- Port Pelican (Approved by Coast Guard/Maritime
Administration) -- Vermillion Block 140, 40 miles offshore Louisiana;
ChevronTexaco; Cost $800 million; Sendout 1.6 Bcf/d; Service 2009; In November
2003, Port Pelican received Coast Guard approval and approval for a deepwater
port license from the Maritime Administration of the Department of
Transportation, paving the way for the company to begin construction. However,
ChevronTexaco pushed back the timing of service from 2007 to 2009 because of
required upstream supply agreements. The terminal potentially could receive LNG
from three proposed liquefaction terminals in Angola, Nigeria and Venezuela.
The Angola and Nigeria liquefaction projects won't be operational until
2009.
- Port Arthur (Pending at FERC) -- Port Arthur, Texas; Sempra
Energy; Sendout 1.5 Bcf/d, expandable to 3 Bcf/d; Cost $600 million; Storage
480,000 cubic meters in three 160,000 cubic meter storage tanks; Service in
2009. The Port Arthur LNG project would feature two unloading berths, and would
be capable of doubling its storage capacity in the future to accommodate three
additional storage tanks and additional facilities.
- Sabine Pass (Approved by FERC) -- Sabine Pass, Louisiana;
Cheniere LNG; Peak sendout 2.6 Bcf/d; Cost $750 million; Three 160,000 cubic
meter storage tanks (10.1 Bcf of storage space); Service in late 2007. Project,
which was approved by FERC in December 2004 would include a 16-mile 42-inch
diameter pipeline that would link the terminal to Natural Gas Pipeline Co. of
America (NGPL) in Johnson's Bayou, LA. From there, the pipeline will extend to
another connection with NGPL and to connections with Transcontinental Gas Pipe
Line, Texas Gas Transmission, Louisiana Resources Pipeline Co. and others
pipelines in the Gulf Coast region. ChevronTexaco Global Gas signed a 20-year
agreement for 700 MMcf/d of reserved regasification capacity. The agreement
also includes options to reduce or expand capacity to 500 MMcf/d or 1 Bcf/d,
respectively. Sabine's other large capacity holder is Total LNG USA with a
reservation for 1 Bcf/d for 20 years starting in April 2009. Cheniere LNG will
retain the balance of the capacity.
- Vista del Sol (Pending at FERC, Received DEIS) -- Quintana
Island, San Patricio County, Texas, about two miles west of Ingleside;
ExxonMobil; Cost $600 million; Sendout capacity 1 Bcf/d; Project also would
include a 25-mile, 36-inch diameter gas pipeline with a capacity to deliver 1.4
Bcf/d of gas. Service expected in 2008. A favorable draft environmental impact
statement was released by FERC in December 2004. ExxonMobil's LNG supply is
expected to come from Qatar. In October, ExxonMobil and Qatar Petroleum
announced an agreement to supply 15.6 million tons a year of LNG, or 2 Bcf/d,
to the United States for 25 years.
Pacific Coast
- Cabrillo Port (Pending at Coast Guard/Maritime Administration and
California State Lands Commission) -- 21.5 miles offshore Oxnard,
California; BHP Billiton; Sendout 0.8 Bcf/d on average and 1.5 Bcf/d at peak;
Storage capacity for 6 Bcf of gas; Cost expected to be $550 million; Service
expected in 2008; Filed with California State Lands Commission and the Coast
Guard for permits.
- Clearwater Port (Pending at Coast Guard/Maritime Administration
and California State Lands Commission) -- offshore Oxnard, California;
Crystal Energy LLC; Sendout 0.8 Bcf/d; Cost $300 million; Service 2007; Filed
with California State Lands Commission and the Coast Guard for permits; Crystal
plans to convert an idled oil platform, Platform Grace, 13 miles offshore
Ventura County, CA, into an import terminal and build a 12.6 mile pipeline to a
connection with Southern California Gas Co.'s backbone pipeline onshore.
Crystal also is working on an LNG supply agreement with the Alaska Gasline Port
Authority. Australia's Woodside Energy Inc. will provide funding to Crystal to
obtain required project approvals through federal, state and local agencies in
exchange for giving Woodside, a major producer on Australia's Northwest Shelf,
preferential access rights to Clearwater's terminal capacity. Woodside also
will help build and will operate the terminal.
- Energy Costa Azul LNG (Approved by State and Federal Mexican
Agencies, including the Comision Reguladora de Energia) -- a few miles
north of Ensenada, onshore Baja California Norte, Mexico; Sempra/Shell; Sendout
1 Bcf/d; Service in 2008; Cost $600 million; Permits have been issued; Road
construction underway; Terminal construction expected to begin before the end
of 2004; Supply agreements being negotiated with the Indonesian government and
BP Indonesia. Shell also will bring LNG supply from the Sakhalin II project in
eastern Russia, where Shell is the largest shareholder. Sempra and Shell said
500 MMcf/d will be used to serve the Mexican gas market and the remaining 500
MMcf/d will serve Southern California and the southwestern United States
through the North Baja pipeline system.
- Jordan Cove (Planned) -- Coos Bay, OR; Energy Projects
Development LLC (EPD) of Evergreen, CO; Average sendout 150 MMcf/d; Cost $150
million; Storage capacity 95,000 cubic meters in one storage tank; Service in
early 2009.
- Kitimat LNG (Planned) -- Kitimat, British Columbia; Galveston
LNG; Sendout 0.34 Bcf/d.
- Lazaro Cardenas (Pending at Mexican Regulatory Agencies) --
Lazaro Cardenas, Mexico on Central Mexico's Pacific Coast; Tractebel/Repsol;
Sendout 0.5 Bcf/d; Tractebel LNG plans to purchase 2.7 million metric tons of
LNG each year for 18 years from Hunt Oil's PERU LNG Co., which is expected to
begin service in Pampa Melchorita, Peru in early 2008.
- Long Beach LNG (Pending at FERC) -- Long Beach, California;
Sound Energy Solutions (Mitsubishi)/ConocoPhillips; Sendout 0.7 Bcf/d; In a
declaratory order issued in March 2004, the Federal Energy Regulatory
Commission said it had exclusive jurisdiction over the terminal under Section 3
of the Natural Gas Act (NGA). The California Public Utility Commission is
challenging that authority at the U.S. Court of Appeals for the DC Circuit. The
CPUC has ruled that the terminal is a utility and falls under state regulatory
authority. FERC also has ruled that the California Coastal Commission has
federally delegated authority over the project under the Coastal Zone
Management Act.
- Offshore California (Planned) -- Offshore California;
ChevronTexaco; Sendout 0.75 Bcf/d.
- Port Westward (Planned) -- St. Helens, Oregon; Port Westward
LNG LLC; 0.7 Bcf/d.
- Prince Rupert (Planned) -- Prince Rupert, British Columbia;
WestPac Terminals; Sendout 0.30 Bcf/d.
- Puerto Libertad (Pending at Mexican Regulatory Agencies) --
Puerto Libertad, Mexico; Gulf of California, Sonora Pacific LNG (DKRW Energy
LLC); Sendout 1.3 Bcf/d; Service in mid-2008; About 500 MMcf/d of regasified
LNG deliveries are expected to be directed to the Sonora marketplace with the
remaining 800 MMcf/d delivered to markets in the southwestern United States via
pipeline connections planned with El Paso Natural Gas, which is building the
pipeline infrastructure. DKRW recently purchased 1,500 acres of property from
the state of Sonora, Mexico.
- Skipanon LNG (Planned) -- Astoria, OR, at mouth of the
Columbia River; Calpine Corp.; Sendout 1 Bcf/d; Cost $500 million; Service
expected in 2011. Calpine envisions building a 41-mile, 36-inch diameter
natural gas pipeline across the Columbia River in an easterly direction to
connect with The Williams Co.'s Northwest Pipeline system at Longview, WA.
- Terminal GNL Mar Adentro (Pending at Mexican Regulatory
Agencies) -- 8 miles offshore Tijuana, Baja California Norte, Mexico near
the Coronado Islands; ChevronTexaco; Average sendout 0.75 Bcf/d with peak
sendout of 1.4 Bcf/d; Cost $650 million; Storage capacity 250,000 cubic meters;
Service in 2009 (pushed back from 2007 to coincide with upstream supply
projects). ChevronTexaco plans to transport LNG from the Gorgon gas fields off
Western Australia to the Baja California terminal using double-hulled LNG
carriers, but the Gorgon liquefaction project also will not be operational
until 2009 or 2010.
Canceled Terminals
- Brownsville -- Brownsville, Texas; Cheniere LNG; Sendout 1.5. The
project was in the early planning stages. Cheniere had an option on a site for
the terminal but never activated it.
- Fairwinds LNG -- Harpswell, ME; TransCanada/ConocoPhillips; Cost
$350 million; Sendout 0.5 Bcf/d; Service 2009; Canceled because of local
opposition; Town residents voted not to lease a former U.S. Navy Fuel Depot
site to build the LNG terminal and regasification facilities. The town is
located 15 miles northwest of Portland, ME.
- Hope Island LNG -- Hope Island, Maine (near Cumberland);
TransCanada/ConocoPhillips; Canceled because of local opposition.
- Humbolt Bay LNG -- Eureka, CA, Samoa Point; Calpine Corp.; Canceled
because of local opposition. Project would have included 155-mile pipeline and
220 MW power plant.
- Mare Island LNG -- Vallejo, CA; Shell US Gas and Power/Bechtel
Enterprises; Cost $1.5 billion; Canceled because of cost, shipping scheduling
and local opposition due to safety concerns. Tankers would be escorted by Coast
Guard under several major bridges including the Golden Gate Bridge and through
San Francisco Bay. Mare Island is a former Navy base located about 25 miles
northeast of San Francisco.
- Navy Homeport LNG -- Mobile, AL, ExxonMobil; Sendout 1 Bcf/d;
Project cost $600 million; Service originally expected in 2009. ExxonMobil paid
$38 million in 2003 for a three-year option on 200 acres of land along Mobile
Bay south of the Mobile city limits. It never filed an application with FERC
for the terminal. A series of articles in the local Mobile Register
newspaper in fall of 2003 highlighted safety issues regarding LNG terminals.
Subsequently, Alabama Gov. Robert Riley warned FERC and the state port
authority that he would block the sale of state-owned land outside of Mobile to
ExxonMobil to site the import terminal unless the agency first conducted an
independent, site-specific study of the potential hazards facing the public.
The company released a statement on Oct. 29, 2004 saying that it was "no longer
in our business interests" to maintain the Alabama State Docks site, the
planned site for the LNG facility, by extending the company's option to
purchase it. ExxonMobil, which had already made $1.5 million in option payments
on the property, said it did not intend to make another $1.5 million payment
that was due Nov. 1.
- New Jersey Energy Bridge -- Belmar, NJ; El Paso Corp.;
Canceled.
- Pinto Island -- Mobile Bay, Alabama; Cheniere LNG; Sendout 1 Bcf/d;
Cheniere had an option on a site but never activated it. There was considerable
local opposition to an LNG terminal being located in Mobile (see Navy Homeport
LNG above).
- Tampa LNG -- Tampa, Florida; BP; Canceled.
- Tijuana Regional Energy Center -- Baja California Norte; Marathon;
Sendout 0.75 Bcf/d; Canceled because of local/political opposition. Mexican
authorities took back property leases Marathon held for the project.
Project also was to include a 1,200 MW power plant, a 20 million gallon
seawater desalinization plant and a wastewater treatment facility. Marathon had
expected to have the complex in service in 2006.
|